The proposed work involves the retention of the facades, gutting the insides of the existing building and reconstruction using steel framing to accommodate 5 new cinema screens, foyer, bar and ancillary space along with 3 private apartments.

The new steel framed structure will have composite floors, all off piled foundations, all construction within the constraints of the retained facades. Stage 4 design is nearing completion and site works are due to start Autumn 2018.